Maintenance and construction work will limit electricity transmission capacity between Sweden and Finland in the summer
The transmission capacity of the cross-border electricity transmission connection between Northern Finland and Sweden will be lower than usual in the summer due to maintenance and construction work on transmission lines. The modifications and measurements carried out during the outage ensure the operational reliability and safety of the cross-border transmission connection.

Work to improve the reliability and operational safety of the cross-border transmission connection will be carried out on transmission lines in northern Sweden in early summer, which is why part of the cross-border electricity transmission connection between Finland and Sweden will be out of service. During the limitation period, the transmission capacity of the connection from Finland to Sweden will be 300 megawatts (usually 1100 megawatts) and the transmission capacity of the connection from Sweden to Finland will be 200 megawatts (usually 1200 megawatts). The estimated duration of the interruptions is just over three weeks.
A similar restriction will be repeated in July and August, when the construction work of the Aurora Line transmission line will continue with an interruption of approximately four weeks. The Aurora Line is a new cross-border transmission connection implemented jointly by Fingrid and Svenska kraftnät, which, when completed in 2025, will significantly increase transmission capacity between Finland and Sweden. The Aurora Line transmission line is 380 kilometres long and runs from the Pyhänselkä substation in Muhos all the way to Messaure in Sweden.
The construction of the first phase of the Aurora Line began in autumn 2022 in Finland. In addition to increasing transmission capacity, Aurora Line will improve the security of electricity supply and the resilience of the electricity system not only in Finland and Sweden, but also more widely in the entire Baltic Sea region.
Restrictions on cross-border transmission connections increase sensitivity to fluctuations in electricity prices
During border capacity limitations, sensitivity to fluctuations in electricity prices increases. In particular, price fluctuations may be greater than usual in situations where there are simultaneously several influencing factors, such as low or high wind power production, disturbances in power plants or disturbances in other transmission connections.
In addition, there will be several outages in Ostrobothnia during the summer because of construction work strengthening the main grid , during which the maximum production of wind power will have to be limited regionally by a maximum of 2,000 megawatts due to system security.
"Cross-border transmission connections to Sweden and Estonia are very important for the functioning of the electricity market and the system security of the Finnish electricity system. At the moment, the main grid is being built at a rapid pace in Finland and Sweden, which also causes restrictions and interruptions in electricity transmission. Fingrid and Svenska kraftnät work closely together on both sides of the border to ensure that necessary outages cause as little inconvenience as possible," says Tuomas Rauhala, Director of Power System Operations at Fingrid.
Additional information:
Senior Advisor Timo Kaukonen, phone +358 40 545 2124
Unit Manager Mikko Piironen, phone +358 50 599 0141
Email addresses are in the format etunimi.sukunimi@fingrid.fi
Keywords
About Fingrid Oyj
Fingrid is Finland’s transmission system operator. We secure reliable electricity for our customers and society, and we shape the clean and market-oriented electricity system of the future.
Fingrid delivers. Responsibly.
www.fingrid.fi
Alternative languages
Subscribe to releases from Fingrid Oyj
Subscribe to all the latest releases from Fingrid Oyj by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Fingrid Oyj
Olkiluoto 3:n järjestelmäsuojan uusi sopimuskausi käynnistyy heinäkuussa30.6.2025 16:19:59 EEST | Tiedote
Energiaviraston päätöksen mukaan Teollisuuden Voima Oyj:n (TVO) Olkiluoto 3 -ydinvoimalaitoksen (OL3) järjestelmänsuojaan osallistuvien kohteiden hankinta on Fingridin tehtävä. Vuoden alusta sovellettu väliaikainen OL3:n järjestelmäsuojajärjestely päättyy kesäkuun 2025 lopussa. Fingrid ja TVO ovat nyt sopineet OL3:n järjestelmäsuojan maksujärjestelyistä ja päivittäisestä tiedonvaihdosta 1.7.2025 alkaen.
Uusi ehdollinen liittymissopimusmalli tukemaan suurten teollisten hankkeiden verkkoliityntä- ja investointipäätösprosesseja24.6.2025 15:11:42 EEST | Tiedote
Fingrid on ottanut käyttöön perinteisen liittymissopimuksen rinnalle ehdollisen liittymissopimuksen. Uuden mallin tavoitteena on tukea ja helpottaa suurten teollisten hankkeiden verkkoliityntä- ja investointipäätösprosesseja, ja se koskee alkuun vähintään 250 megawatin suuruisia laajoja, luvitukseltaan pitkäkestoisia kulutushankkeita. Mallia on tarkoitus kehittää kattamaan jatkossa myös suuret tuotantohankkeet.
Uusiutuvan energian hankkeita pidetään tärkeinä vihreän siirtymän mahdollistamiseksi24.6.2025 09:05:00 EEST | Tiedote
Suomalaiset suhtautuvat myönteisesti vihreään siirtymään ja sitä tukeviin uusiutuvan energian hankkeisiin, mutta kolmannes ei ole valmis hyväksymään merkittäviä muutoksia omassa arjessaan niiden edistämiseksi. Mitä paremmin vihreä siirtymä ymmärretään, sitä tärkeämpänä sitä pidetään. Suhtautuminen vihreän siirtymän hankkeisiin on kriittisempää, kun niitä suunnitellaan lähelle omaa elinympäristöä. Tulokset käyvät esille Fingridin teettämästä kuluttajatutkimuksesta.
EstLink 2 -sähkönsiirtoyhteys palaa kaupalliseen käyttöön perjantaina18.6.2025 14:48:00 EEST | Tiedote
Suomen ja Viron välisen sähkönsiirtoyhteyden korjaustyöt ovat valmistuneet ja yhteyden odotetaan palaavan kaupalliseen käyttöön perjantaina 20.6. Sähkönsiirtoyhteys on ollut poissa käytöstä joulukuusta lähtien.
EstLink 2 electricity transmission link returns to commercial use18.6.2025 14:48:00 EEST | Press release
The repair work on the electricity transmission link between Finland and Estonia has been completed, and the link is expected to return to commercial use on Friday, June 20th. The transmission link has been out of service since December.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom