A new football stadium to Tapiola Sports Park
The project plan for the construction of the football stadium in Tapiola Sports Park will soon be discussed by the City Board. The aim is that construction work will begin in 2026, and the stadium will open for football games in season 2029.

The development of Tapiola Sports Park takes a big step forward when the project plan for the construction of the Tapiola Sports Park's football stadium is transferred to the City Board. The reform of the area began by the start of the planning project in December 2019, and the Council approved the plan in April 2021. The decision was appealed to the Helsinki Administrative Court, which rejected the appeal in August 2022. The plan legally entered into force in October 2022.
The new football stadium makes it possible to organise international games and major events. The capacity of the stadium is approximately 6,000 seats. All seats will be under shelter. A parking area for the Sports Park will be located under the stadium, with approximately 670 parking spaces. Approximately 150 parking spaces will be created as a temporary solution on the eastern side of the stadium, where the planned multi-purpose hall would be. Residential blocks will be built on top of the parking area deck on the western edge of the stadium block.
No changes will be made to the existing sports buildings, i.e. ice skating halls, Honkahalli and the old sports hall.
“The Tapiola Sports Park renovation project has been long time coming. With the reform, the area will become an easily approachable and versatile centre for sports and events,” says Olli Isotalo, Urban Environment Director.
Operating of the existing sports halls taken into account in the construction
The companies KOy Tapiolan Stadion and KOy Tapiolan Urheilupuiston Pysäköinti have been established tom carry out the process for the construction of the stadium and the underground parking facility. The companies are 100% owned by the City of Espoo. The companies will organise competitive tendering on the contract for the construction of the stadium block.
The estimated investment cost of the football stadium and the parking facility is EUR 74 million.
The tendering process for the project will take place in the first half of 2025. According to the current estimate, the construction of the stadium could begin in 2026 and be completed in 2029.
The construction work will be carried out in phases, taking into account the operating conditions of the existing sports halls and ice skating halls.
The Public Works Department will design and build other sports facilities in the area, municipal engineering and streets simultaneously with the stadium project.
The City Board will discuss the project plan of the Tapiola Football Stadium on Monday 3 March 2025.
Keywords
Contacts
Olli IsotaloDeputy Mayor for Urban Environment
Tel:+358 50 593 3359olli.isotalo@espoo.fiJarmo KulmalaProject Director
Tel:+358 43 826 6846jarmo.kulmala@espoo.fiImages

Links
Alternative languages
Subscribe to releases from Espoon kaupunki - Esbo stad
Subscribe to all the latest releases from Espoon kaupunki - Esbo stad by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Espoon kaupunki - Esbo stad
Kommunerna längs Västbanan och staten har enats om att föra järnvägsprojektet vidare till byggfasen – kommunerna nöjda med det äntligen uppnådda förhandlingsresultatet31.10.2025 17:30:30 EET | Pressmeddelande
I förhandlingarna mellan staten och delägarkommunerna i Västbanan Ab – Esbo, Åbo, Salo, Lojo, Vichtis och Kyrkslätt – har parterna nått en överenskommelse om att föra Västbanan vidare till byggfasen. Aktieägaravtalet gällande finansieringen av projektet kommer att behandlas av beslutsorganen i de sex kommunerna och hos staten under november–december. Byggandet av Västbanan kan inledas i slutet av år 2027.
Länsiradan kunnat ja valtio sopivat ratahankkeen etenemisestä rakentamisvaiheeseen – kunnat tyytyväisiä vihdoin saavutettuun neuvottelutulokseen31.10.2025 17:30:30 EET | Tiedote
Länsirata Oy:n osakaskuntien Espoon, Turun, Salon, Lohjan, Vihdin ja Kirkkonummen sekä valtion välisissä neuvotteluissa on saavutettu sopu, jonka pohjalta voidaan siirtyä päätöksentekoon Länsiradan etenemisestä rakentamisvaiheeseen. Hankkeen rahoitusta koskeva osakassopimus viedään Länsiradan kuuden kunnan ja valtion päätöksentekoelimiin marras-joulukuussa. Länsiradan rakentaminen voisi alkaa vuoden 2027 lopulla.
Ympäristö- ja rakennuslautakunta: rakennusjärjestyksen luonnos nähtäville31.10.2025 09:03:45 EET | Tiedote
Espoon ympäristö- ja rakennuslautakunta päätti kokouksessaan 30.10.2025 asettaa Espoon rakennusjärjestysluonnoksen nähtäville ajalle 5.11.–5.12.2025. Esittelijän kokouksessa muuttama ehdotus hyväksyttiin yksimielisesti. Sen myötä luonnoksen sanamuotoja tarkennettiin ja siitä poistettiin epätarkoituksenmukaisia kohtia. Rakennusjärjestysluonnoksen muokattu versio julkaistaan keskiviikkona 5.11.2025 kokouksen pöytäkirjan yhteydessä.
Info från nämnden Svenska rum 30.10.202530.10.2025 18:25:09 EET | Pressmeddelande
På torsdagens möte fastställde nämnden de svenskspråkiga förskolornas, grundskolornas och gymnasiets arbets- och lovtider för de två följande läsåren samt godkände antagningskriterierna till idrottslinjen i Mattlidens gymnasium från och med hösten 2026.
Tiedote kasvun ja oppimisen lautakunnan kokouksesta 29.10.202529.10.2025 21:26:41 EET | Tiedote
Kasvun ja oppimisen lautakunta päätti kokouksessaan suomenkielisen varhaiskasvatuksen, perusopetuksen ja lukiokoulutuksen työ- ja loma-ajoista lukuvuosille 2026–2027 ja 2027–2028.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom