Fennovoima has terminated the contract for the delivery of the Hanhikivi 1 nuclear power plant with Rosatom
This means, that cooperation with RAOS Project is terminated with immediate effect and both the design and licensing work and works at the Hanhikivi 1 site with RAOS project end.
“Unfortunately, the termination of the EPC contract is estimated to have a significant employee impact in Fennovoima and is expected to impact also the supply chain companies and Pyhäjoki region. Our main objective is to support our employees by keeping them informed and work in close cooperation with both our employees and employee representatives. In addition, we focus on preserving the site,” says Joachim Specht, Fennovoima’s CEO.
“The decision to terminate the EPC contract with RAOS Project is not made lightly. In a such a large project there are significant complexities and decisions are made only after thorough considerations. We fully acknowledge the negative impacts and do our best to mitigate those,” says Esa Härmälä, chairman of the Board.
Fennovoima will provide further information and answer possible questions during a press conference on Monday May 2nd. At this point we do not provide separate one-to-one interviews. The event will be held at Technopolis premises in Helsinki, Salmisaari, Hiilikatu 3 beginning at 12:00.
Questions will be answered by CEO Joachim Specht and the Chairman of the Board Esa Härmälä.
Participants are kindly requested to inform in advance, please send an e-mail to communications@fennovoima.fi. When registering, please state the name of the participant and the media represented.
About Fennovoima Oy
Fennovoima is a nuclear energy company established to meet the energy needs of Finnish enterprises. Hanhikivi 1 nuclear power plant will generate approximately 10 percent of Finland’s electricity needs – reliably, and with no emissions.
Subscribe to releases from Fennovoima Oy
Subscribe to all the latest releases from Fennovoima Oy by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Fennovoima Oy
Fennovoima cuts its activities significantly22.6.2022 14:06:22 EEST | Press release
On 10 May 2022, Fennovoima started the change negotiations, concerning its entire personnel. The change negotiations ended on 21 June. As a result of negotiations, Fennovoima will significantly reduce its operations. Staff terminations will be implemented during 2022. Before the reductions Fennovoima has 356 employees and at the beginning of 2023 Fennovoima will have less than 10 employees.
Fennovoima supistaa toimintojaan voimakkaasti22.6.2022 14:04:26 EEST | Tiedote
Fennovoima käynnisti 10.5.2022 koko henkilöstöä koskevat muutosneuvottelut, jotka päättyivät 21.6. Neuvotteluiden tuloksena Fennovoima supistaa toimintojaan voimakkaasti. Henkilöstövähennykset toteutetaan vuoden 2022 aikana. Ennen henkilöstövähennyksiä Fennovoimalla on 356 työntekijää ja vuoden 2023 alussa alle 10 työntekijää.
Fennovoima has withdrawn the Hanhikivi 1 Construction License Application – focus is now on preserving the Pyhäjoki site24.5.2022 09:35:07 EEST | Press release
On Tuesday 24th May 2022, Fennovoima has withdrawn the Hanhikivi 1 nuclear power plant Construction License Application. On 2nd May 2022, Fennovoima announced that it had terminated the EPC contract of plant delivery with RAOS Project due to RAOS Project’s significant delays and inability to deliver the project.
Fennovoima peruu Hanhikivi 1 -ydinvoimalan rakentamislupahakemuksen – keskittyy Pyhäjoen työmaan ylläpitämiseen24.5.2022 09:31:20 EEST | Tiedote
Fennovoima on tiistaina 24.5. perunut Hanhikivi 1 -ydinvoimalan rakentamislupahakemuksen. Yhtiö tiedotti 2.5. päättäneensä RAOS Projectin kanssa solmitun laitostoimitussopimuksen johtuen RAOS Projectin merkittävistä viiveistä ja kyvyttömyydestä toteuttaa hanke.
Fennovoima on päättänyt Hanhikivi 1 -ydinvoimalan laitostoimitussopimuksen Rosatomin kanssa2.5.2022 10:01:41 EEST | Tiedote
Fennovoima on päättänyt RAOS Projectin kanssa solmitun laitostoimitussopimuksen johtuen RAOS Projectin merkittävistä viivästyksistä ja kyvyttömyydestä toteuttaa Hanhikivi 1 -hanke. Viime vuosien aikana toimittajan merkittävät viivästykset ovat jatkuneet ja kasvaneet. Sota Ukrainassa on pahentanut hankkeen riskejä, joita RAOS Project ei ole kyennyt ehkäisemään.